Liquefaction Expansion / Project Timeline

Expansion Project timeline

In May 2016, Cameron LNG received Federal Energy Regulatory Commission (FERC) authorization to proceed with Expansion of the existing liquefaction export project (2 additional trains). Cameron LNG has received authorization from the Department of Energy (DOE) to export LNG produced from the Expansion project to all current and future Free Trade Agreement (FTA) and non-FTA countries.

February 2015

DOE: Filed FTA permit application

February 2015

FERC: Submitted request to initiate pre-filing review process

May 2015

DOE: Filed non-FTA permit application

May 2015

Cameron Open House

July 2015

FTA application approved

July 2016

Non-FTA application approved

2015-2016

Permitting activities with FERC and DOE

Stakeholder engagement activities

2017

Begin construction of expansion project

2019

Project completion